Construction Progress

Drake Avenue Apartments

Construction Progress

Updated April 23rd, 2025

 

4/21/2025 to 5/04/2025

  • Stake & Cut Bench at A Beams
  • Continue Drilling and Pouring at P & A Beams
  • Lagging at P & W Beams
  • Backfill, drain and waterproof at P Beams
  • Lagging at A Beams
  • Backfill, drain and waterproof at A Beams
  • Shotcrete P & A Beams
  • Grouting and testing at tiebacks
  • Backfill at P Beams
  • Continuation of dirt moving
  • Continuation of dirt off haul from site
  • Import and placement of rock and other material onsite
  • Ongoing maintenance and replacement of erosion controls
  • Stocking of shoring material on site

 

05/05/2025 to 05/18/2025

  • Continue waterproofing and backfill
  • Continue shotcrete
  • Grading at east PL
  • Install Fence @ North Wall
  • Sleaving for lights and EV
  • Continuation of dirt moving
  • Continuation of dirt off haul from site
  • Import and placement of rock and other material onsite
  • Ongoing maintenance and replacement of erosion controls

 

05/19/2025 to 06/01/2025

  • Grade and stake for slabs
  • Form for slab through M5 Line
  • Stake for unit bolting and hardware
  • Rebar inspection
  • Pour slab
  • Tap Water to Back of Walk
  • Joint Trench
  • Finish grade at site
  • Dirt moving
  • Dirt off haul from site
  • Import and placement of rock and other material onsite
  • Ongoing maintenance and replacement of erosion controls
  • Stocking of shoring material on site
  • Building shoring wall installation – drilling, concrete, placing steel

 

Grading, dirt off haul, shoring walls require large tractors, trucks, drill rigs, concrete trucks, and other equipment. You can expect this equipment to be running for most of the day while these activities are ongoing.  When placed in reverse, trucks, tractors, and other equipment will beep which is an OSHA requirement and cannot be turned off.

This schedule is subject to change without notice.