Construction Progress

Drake Avenue Apartments

Construction Progress

Updated November 6, 2024

11/11/2024 to 11/24/2024

  • Dirt Moving
  • Dirt off haul from site
  • Maintenance and replacement of erosion controls
  • Import and placement of rock and other material onsite
  • Stocking of shoring material on site
  • Start of shoring wall installation

 

11/25/2024 to 12/8/2024

  • Continuation of dirt moving
  • Continuation of dirt off haul from site
  • Import and placement of rock and other material onsite
  • Ongoing maintenance and replacement of erosion controls
  • Stocking of shoring material on site
  • Continuation of shoring wall installation – drilling, concrete, placing steel

 

12/9/2024 to 12/22/2024

  • Continuation of dirt moving
  • Continuation of dirt off haul from site
  • Import and placement of rock and other material onsite
  • Ongoing maintenance and replacement of erosion controls
  • Stocking of shoring material on site
  • Continuation of shoring wall installation – drilling, concrete, placing steel

 

Grading, dirt off haul, shoring walls require large tractors, trucks, drill rigs, concrete trucks, and other equipment. You can expect this equipment to be running for most of the day while these activities are ongoing.  When placed in reverse, trucks, tractors, and other equipment will beep which is an OSHA requirement and cannot be turned off.

This schedule is subject to change without notice.