Construction Progress

Drake Avenue Apartments

Construction Progress

Updated July 7th, 2025

 

07/07/2025 to 07/20/2025

  • Ongoing maintenance and replacement of erosion controls
  • Off haul of surplus dirt and rock
  • Building shoring wall installation – drilling, concrete, placing steel, lagging, welding, nelson stud install and grouting
  • Under slab/ back of wall drainage
  • Structural excavation for slabs/ footing, formwork, rebar and reinforcing
  • Concrete pours
  • Waterproofing of building walls
  • Underslab plumbing and electrical connections
  • Misc site utilities
 

7/21/2025 to 8/3/2025

  • Ongoing maintenance and replacement of erosion controls
  • Off haul of surplus dirt and rock
  • Structural excavation for slabs/ footing, formwork, rebar and reinforcing
  • Concrete pours
  • Waterproofing of building walls
  • Underslab plumbing and electrical connections
  • Misc site utilities
 

8/4/2025 to 8/17/2025

  • Ongoing maintenance and replacement of erosion controls
  • Off haul of surplus dirt and rock
  • Structural excavation for slabs/ footing, formwork, rebar and reinforcing
  • Concrete pours
  • Underslab plumbing and electrical connections
  • Misc site utilities

 

Grading, dirt off haul, shoring walls require large tractors, trucks, drill rigs, concrete trucks, and other equipment. You can expect this equipment to be running for most of the day while these activities are ongoing.  When placed in reverse, trucks, tractors, and other equipment will beep which is an OSHA requirement and cannot be turned off.

This schedule is subject to change without notice.